Team E Meeting Minutes

Wednesday, October 6, 1999

Scott’s Office

3:00pm

 

In Attendance at 3:00pm:

Scott Hancock, Vishal Golia, and Greg Sitrick.

 

I.  Project Schedule

 

We worked as a team to develop a preliminary schedule.  On Thursday, the next day, Greg and Vishal met again to revise the schedule.  Now we need to meet again today as a team at 2:45pm, 10-8-99.  We will bring together any more ideas we have on the schedule before the weekend.  Vishal and Scott can finish any final touches to the schedule, as necessary.

 

II.  Design Plan

 

The design plan, due on Monday, was originally prepared by Greg.  Greg and Vishal also made some revisions to this document on Thursday.  Scott applied these changes and has made further changes to the document.  In our meeting at 2:45 today, we will need to finalize this document.

 

III.  Schedule to Meet with Lee Payne        

 

October 26, 1999, is the day we would like to meet with Lee Payne.  We need to contact him and try to arrange this meeting.